Home / Projects / Spot Cooling for Heat-Source Workstations in a Hardware Foundry Workshop

Spot Cooling for Heat-Source Workstations in a Hardware Foundry Workshop

Industry:Hardware foundry Location:Industrial zone, northern Vietnam Scale:Single-storey steel-structure workshop, several heat-source workstations Timeline:1 week survey + 2 weeks pilot + full-line implementation2026-11-01
Spot Cooling for Heat-Source Workstations in a Hardware Foundry Workshop

Note:These cases are compiled from typical industry scenarios. Customer names are withheld under commercial confidentiality agreements; equipment quantities shown are typical configuration ranges, and performance descriptions are subject to site survey data and acceptance re-testing, and are not offered as committed values.

Project overview

Industry type
Hardware foundry (melting, pouring, cleaning processes)
Workshop conditions
Single-storey steel structure, high clearance, noticeable heat build-up from roof solar gain
Retrofit scope
Spot cooling at heat-source workstations + overall workshop airflow organization
Delivered scope
Site survey, scheme design, equipment supply and installation, effect re-testing

Project Background

The enterprise is a hardware foundry with melting, pouring and cleaning processes concentrated in a single workshop bay. During summer production hours, the working environment at operator positions close to the heat sources was markedly hotter than elsewhere in the workshop, leading to a high shift-rotation frequency and affecting both summer recruitment and on-post retention.

The customer's initial idea was to "bring down the temperature of the whole workshop". The site survey revealed a large workshop volume with dispersed heat sources; a full-workshop cooling design would have pushed both equipment investment and operating electricity cost sharply upward, while the cooling capacity could not be concentrated where people actually stand. The scheme was therefore reframed as spot cooling centered on the heat-source workstations, with overall workshop ventilation as a supporting measure.

Issues Found During the Site Survey

  • Radiant heat is the main cause: measurement data showed the globe temperature at the workstations was clearly higher than the dry-bulb temperature, indicating that the heat felt by workers came mainly from directional radiation from the melting furnace and hot castings, rather than from a rise in general air temperature.
  • Disorganized airflow: the existing wall fans each blew in their own direction without forming a defined intake-to-exhaust path, so hot air accumulated beneath the roof and the temperature rose toward the ridge.
  • Fixed positions, no coverage: the workstations were fixed, but the mounting positions and angles of the existing fans were not aimed at them, and most of the airflow was wasted on unoccupied areas.
  • Insufficient exhaust: side-wall exhaust fans existed, but the number and placement of the units in operation were not matched to the supply air, so no effective cross-draught was formed.

Scheme Design

Based on the survey findings, the scheme was designed in the order of "block radiation first, then supply air, then remove heat":

  1. 1Heat-source shielding and local heat removal: thermal barriers were installed in directions with high radiant intensity to reduce direct radiation onto the workstations; extraction hoods were added at processes with concentrated local heat generation so that heat is carried away near its source.
  2. 2Workstation spot air supply: air supply units were re-arranged according to workstation positions, with mounting height and outlet angle adjusted so that the airflow covers the operator's upper-body working zone while staying within the air velocity allowed by the process.
  3. 3High-volume, low-speed fans: industrial large-diameter fans were arranged where the clearance height permitted, driving slow overall air movement to break up the thermal stratification under the roof, so accumulated hot air joins the circulation and is exhausted.
  4. 4Matched negative-pressure exhaust: the number and position of exhaust units were calculated and adjusted against the supply air volume to form a directional path of "low-level intake, through the workstation, high-level discharge".
  5. 5Electrical and environmental adaptation: motors and control cabinets were selected for dusty, high-temperature environments and equipped with overload and phase-loss protection; maintenance access and the safe clearance to lifting equipment were checked at the same time.

Typical Configuration (subject to site survey)

  • Industrial high-volume fans (high-airflow, low-speed type): coverage radius per unit and the number of units determined by workshop span and clearance height
  • Workstation air supply units: one unit per heat-source workstation, with adjustable angle
  • Negative-pressure exhaust fans: quantity calculated from supply/exhaust balance, placed on the side where hot air accumulates
  • Evaporative air coolers (optional): supplementary cooling in the dry season, depending on local humidity conditions
  • Thermal barriers and local extraction hoods: custom-built to the dimensions of the radiation sources
  • Control and protection: group control, overload and phase-loss protection, start/stop zoning by shift team

Implementation Process

  1. 1Baseline measurement: measurement points were placed at the workstation working height and in a non-supplied control area, continuously recording dry-bulb temperature, relative humidity, air velocity and globe temperature for several days before the retrofit to establish a comparison baseline.
  2. 2Small-scale pilot: two typical heat-source workstations were fitted first to verify the effect of air velocity on the processes (pouring, grinding), the noise level and worker acceptance.
  3. 3Scheme fine-tuning: outlet angles, mounting heights and exhaust matching were adjusted based on pilot feedback, confirming that neither the process nor dust control was affected.
  4. 4Full-line implementation: batch installation was carried out according to the pilot conclusions, with electrical protection, group control and safety guarding completed in parallel.
  5. 5Re-testing and acceptance: re-measurement was performed on typical hot summer days using the same method at the same points, compared against the baseline data, and combined with feedback from the stationed workers to form the acceptance record.

Results and Verification

Acceptance does not use unverifiable statements such as "how many degrees the overall temperature dropped"; verification is carried out as follows:

  • Objective data comparison: dry-bulb temperature, globe temperature and air velocity before and after the retrofit, compared at the same points, in the same time window and with the same measurement method.
  • Control-point cross-check: comparison against a control point in the non-supplied area over the same period, to rule out interference from weather differences.
  • Perceived comfort evaluation: subjective feedback collected from the stationed workers to corroborate the objective data.
  • Operation records: equipment operating power and start/stop strategy were logged and operating cost calculated, providing a basis for later optimization.

Note: the cooling effect is influenced by heat source intensity, workshop volume, ventilation conditions and local climate. Specific values must be based on the site survey and acceptance re-testing; no numerical commitment is made at the scheme stage.

Reusable Lessons

  • Measure before designing: the difference between globe temperature and dry-bulb temperature quickly reveals the share of radiant heat, and directly determines whether the scheme should be shielding-led or ventilation-led.
  • Supply and exhaust must be designed as a pair: adding supply air without adding exhaust creates positive-pressure stuffiness, which feels worse.
  • The pilot phase cannot be skipped: process constraints in hot workshops (the effect of air velocity on pouring, spraying and dust) only surface during a pilot.
  • Air velocity affects perceived comfort more than air temperature: in many situations the workers' sense of improvement comes mainly from airflow and reduced radiation, so acceptance should look at temperature, air velocity and radiation together.

Results and verification

Airflow organization
Changed from disordered air supply to a directional path with a clear hot-air discharge route
Workstation coverage
Air supply units positioned per workstation, concentrating airflow on the working zone
Radiation control
Shielding installed in the direction of the heat sources, reducing direct radiation
Acceptance method
Before/after comparison at the same points, same time window, same method, plus worker feedback