Note:These cases are compiled from typical industry scenarios. Customer names are withheld under commercial confidentiality agreements; equipment quantities shown are typical configuration ranges, and performance descriptions are subject to site survey data and acceptance re-testing, and are not offered as committed values.
Project overview
Industry type
Electronics assembly manufacturing (multiple workshops, multiple shifts)
Retrofit scope
Incoming-line main meter + workshop secondary metering + key equipment tertiary metering
System architecture
Smart electricity meters to edge gateways to energy management platform
Delivered scope
Metering point design, meter and gateway deployment, platform configuration, reports and alarm rules
Project Background
The plant comprises several production workshops and utility stations, and previously had only the monthly total meter bill from the power utility. Management wanted to reduce electricity cost but could not answer several basic questions: which workshop consumed the most, whether no-load operation existed on rest days, how efficiently the compressed air station was running, and whether energy consumption per unit of product was deteriorating.
Without sub-metered data, energy retrofit could only proceed on experience, and its effect could not be demonstrated afterwards. The project objective was therefore defined as: first establish a traceable energy data foundation, then use it to select retrofit items.
Current Situation and Difficulties
- Metering gaps: only the main incoming line was metered; workshops and utility stations had no independent metering, so internal consumption could not be allocated.
- Inconsistent meter protocols: some distribution cabinets were fitted with smart meters and some only with mechanical ones, and meters from different batches differed in communication protocol and parameters.
- Constrained cabling conditions: the workshops are spread far apart, making cross-workshop cabling costly and difficult to coordinate.
- Network and security requirements: the production network and office network had to be segregated, data could not be exported at will, and the remote maintenance channel had to be controlled.
Scheme Design
Metering Point Design (Three Tiers)
- Tier 1: the plant's main incoming line, used for bill reconciliation and total-volume balance verification.
- Tier 2: independent metering for each workshop and utility station (compressed air station, chiller station, pump room), used for departmental assessment and horizontal comparison.
- Tier 3: separate metering for key equipment with high power and long running hours, to pin down the main sources of consumption.
The point design follows the principle of "cover the main energy consumers first, do not over-deploy meters": tier-3 metering targets only equipment with a high share of consumption, avoiding investment with low marginal benefit.
Acquisition Architecture
- One edge gateway is deployed in each distribution room to collect meter data locally in that area. The gateways support multiple serial ports and network ports, and zoning by area reduces long-distance cabling.
- Communication uses the standard Modbus protocol where possible; incompatible legacy meters are resolved by replacement or by adding meters with communication capability.
- Offline buffering and time synchronization are configured on the gateway side to ensure no data loss and no time-sequence misalignment.
- Uplink traffic reaches the locally deployed energy management platform over the plant's internal network, with the production network and office network segmented and isolated.
Platform Functions
- Energy consumption daily reports and monthly comparisons by workshop, by shift and by equipment.
- Energy consumption per unit of product (energy intensity) indicator, combined with output data to analyze true efficiency.
- Peak/flat/valley electricity analysis combined with time-of-use tariffs to assess load-shifting potential.
- Anomaly alarming: abnormal base load during non-production hours, equipment no-load operation, low power factor.
Typical Configuration (subject to site survey)
- Smart electricity meters: configured for tier-1, tier-2 and tier-3 metering points, preferring products with standard communication interfaces
- Edge gateways: deployed by distribution room, industrial-grade wide-temperature, multi-serial-port, with offline buffering support
- Acquisition server/platform: deployed on-premise or in the cloud, handling storage, visualization, reporting and alarming
- Network: production and office networks segmented; remote maintenance through a controlled channel
- Time synchronization: a unified time source to ensure sub-metered data can be compared over the same period
Implementation Process
- 1Point design and survey: check distribution cabinet space, current transformer specifications and power-outage windows, and determine constructible points plus the list of new meters.
- 2Single-point pilot: complete a full-chain validation from meter through gateway to platform in one workshop, confirming protocol, polling cycle and data accuracy.
- 3Total-volume balance verification: compare the sum of sub-meters with the main meter; if the deviation exceeds the threshold, inspect wiring and range settings. Only after the verification passes does the analysis phase begin.
- 4Phased rollout: implement batch by batch by workshop, establishing point naming conventions and alarm rule templates in parallel.
- 5Rule tuning: adjust alarm thresholds and report definitions based on operating data, and assign the responsible department and assessment mechanism.
Results and Verification
Project delivery takes "usable, traceable data" as the core acceptance criterion:
- Data completeness: sub-metered data is collected continuously, can be backfilled after network outages, and gaps are flagged.
- Total-volume balance: the sum of sub-meters at each tier stays within a reasonable deviation of the main meter.
- Usability: reports by workshop and shift can support management assessment and horizontal comparison.
- Analysis output: energy-saving directions worth prioritizing were identified (for example no-load operation during non-production hours, compressed air system operating strategy, power factor correction), together with pre-retrofit baseline data.
Note: energy-saving benefits depend on the subsequent retrofit items and on-site operating conditions, and must be calculated from same-period before/after comparison data; no specific energy-saving percentage is promised at the scheme stage.
Reusable Lessons
- Do the balance verification before any analysis: if sub-meters do not reconcile with the main meter, there is a wiring or range problem, and every analysis conclusion at that point is untrustworthy.
- Set the sampling interval as needed: an interval of 1 to 5 minutes is sufficient for energy analysis; full-rate second-level acquisition only adds storage and network burden.
- Time synchronization is the hidden prerequisite: if clocks differ between workshops, sub-metered curves cannot be compared over the same period and the energy analysis is distorted.
- An owner must be assigned: if nobody reads the reports and nobody acts on the alarms, the system will be idle within six months, so the responsible department must be named at project start.
Results and verification
Energy visibility
Broken down by workshop, shift and key equipment; daily and monthly comparisons available
Data quality
Offline buffering with backfill, gap flagging, total-volume balance verification passed
Anomaly detection
Base load during non-production hours and no-load operation identifiable and alarmable
Retrofit basis
Pre-retrofit baseline data established to support later savings calculations